Within this area, construction will occur in three general phases:
- Northbound traffic will be shifted west to construct two northbound outside lanes and the shoulder.
- Northbound traffic will be shifted east so the Express Lanes can be constructed in the center median.
- Southbound traffic will be shifted east to construct southbound outside lanes and shoulder.
Across the corridor, the Express Lanes project will increase capacity, replace four aging bridges and widen four additional bridges, provide multimodal access to regional transit, and create new pedestrian and bicycle access under I-25 at Kendall Parkway. For more information on the project, view the CDOT press release.