Thursday, August 27, 2020

Bridge work requires full night closures of I-25 and Prospect Road Sept. 1 and 8

 

Expect nighttime closures of North I-25 at Prospect Road and at Prospect Road between the on- and off- ramps on the nights of September 1st and 8th. During the closure, the deck for the new Prospect Road bridge will be poured for the north portion of the bridge. 

Once completed, the Prospect Road bridge will have two through lanes, center turn lanes in each direction, and a bike and pedestrian multi-use path.

For more information, including the recommended detour, visit https://www.codot.gov/news/2020/august-2020/bridgeworknews.